What is a bill of quantities in construction contracts?

A bill of quantities lists a project's work items with each item's quantity and unit rate. It is the basis for pricing the contract and measuring the work done in each progress claim.

Bill of quantities (BOQ)In Arabic: جدول الكميات

The term explained

The quantities carried out in each progress claim are compared with the bill, and anything outside it is handled with a variation order. An accurate bill reduces disputes with the owner over payment.